Full Bathroom Remodeling in Calabasas, CA: What It Costs and How Long It Takes
Full Bathroom Remodeling in Calabasas, CA runs $9,000 – $28,000 for most homes, and a typical gut remodel takes 3 to 5 weeks of working time from demo to final inspection. That range covers new tile, a new layout where needed, fixtures, vanity, waterproofing and finish work done to code. Every Calabasas job starts with a free on-site estimate at (888) 427-1733, where we measure the room, check the plumbing and framing, and write a line-item quote before anything gets ordered.
How We Run a Full Bathroom Remodel, Stage by Stage
We don’t hand you a three-week window and disappear. Here’s what actually happens, in order, and where you make decisions.
Stage 1: Site protection and demo (days 1-3)
We lay floor protection from the front door to the bathroom, seal off the room with plastic and a zip wall, and shut the water at the fixture valves before a hammer swings. Demo pulls out the old vanity, toilet, tub or shower, tile and drywall down to studs where the layout requires it. You decide one thing here: whether anything stays. Saved tub? Saved cabinet box? Say it before day 1, not after the dumpster arrives.
Stage 2: Rough-in and inspection (days 3-6)
This is the stage that separates a real remodel from a cosmetic resurfacing. The plumber moves supply and drain lines, the electrician runs new circuits for lighting, exhaust fan and any heated floor, and we frame any wall changes. Then the city inspects the rough work before a single tile goes up. In Calabasas hillside homes this is also where we confirm the floor framing can carry a heavier tile or stone assembly.
Stage 3: Waterproofing and substrate (days 6-9)
We hang cement board or a foam tile backer, tape and mud the seams, then roll on a bonded waterproof membrane throughout the wet area. A curbless shower gets a sloped mortar bed built to the drain. This stage is invisible once tile lands, which is exactly why so many remodels fail a few years later. You decide tile layout and grout joint width now, because the substrate depth depends on it.
Stage 4: Tile, fixtures and finishes (days 9-20)
Wall and floor tile go in, then grout cures before we set the toilet, vanity, faucets, shower trim and glass. Cabinets and the countertop get templated mid-stage, so expect a 3 to 5 day gap on stone. This is where your finish choices either hold the timeline or stretch it. Pick everything before demo, not during.
Stage 5: Punch, inspection and walkthrough (days 20-25)
The city signs off on the final inspection, we do a full punch list, and we walk the room with you. Every job is covered by our 730-Day Done Right Promise – if it’s not right, we make it right. That guarantee covers the workmanship, not just the materials.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Actually Define Your Bathroom
These are the decisions that move both the look and the budget:
- Tile material. Porcelain runs $4 – $12 per square foot and handles moisture well. Natural stone like marble or travertine looks richer but costs $12 – $30+ per square foot, needs sealing annually, and shows water spotting on shower floors.
- Shower configuration. A tiled shower with a linear drain and frameless glass is the current standard. A tub-and-shower combo saves space and money but limits the feel of the room.
- Vanity and countertop. Stock cabinets in the $800 – $3,000 range work fine. Custom cabinetry with a quartz top pushes past that. Cambria and similar quartz brands hold up better than marble in a wet room.
- Fixtures. Kohler-tier faucets and shower valves cost more up front but have replaceable cartridges. Builder-grade fixtures cost less and fail faster.
- Ventilation. A properly sized exhaust fan vented to the exterior matters more in a Calabasas home than most people realize – poor venting is the number one cause of mold behind tile.
- Heated flooring. Worth the $800 – $1,500 in a room with a cold tile floor. Optional, but a common add.
What Full Bathroom Remodeling Costs in Calabasas, CA
Expect $9,000 – $28,000 for a full bathroom remodel in Calabasas. A compact hall bath with stock materials lands near the low end. A primary bath with a curbless shower, stone tile and custom vanity lands at the top.
What pushes a job toward $28,000:
- Room size. A primary bath at 80 – 100 square feet uses roughly double the tile and material of a 40-square-foot hall bath.
- Relocating plumbing. Moving a drain or supply line across the slab or through framing adds real cost. Keeping fixtures in place saves money.
- Structural changes. Removing a wall or adding a beam to open the room requires engineering.
- Material grade. Porcelain versus stone, stock versus custom cabinetry, standard versus designer fixtures.
- Permit and inspection scope. A full gut remodel with plumbing and electrical changes requires permits and inspections. Skipping them can void your insurance and hurt resale.
Your written estimate itemizes demo, rough-in, waterproofing, tile, fixtures, labor and permits. It does not include change orders you request mid-job or unforeseen rot behind the wall – we flag those the moment we find them, with a price, before proceeding. Upfront pricing, no surprises. If you’re already planning other exterior work, homeowners often pair this with Roof Repair in Calabasas while crews are on site.
See the difference
Before
After
Before
After
Before
AfterWhat Calabasas Homes Specifically Do to This Job
Calabasas sits in the Santa Monica Mountains foothills, and that changes the job. Much of the housing stock is hillside and canyon property – large Mediterranean and Spanish-style estates in gated communities like The Oaks, Calabasas Hills and Mulholland Heights, alongside 1960s-70s ranch homes and newer rebuilds. On slopes, a bathroom remodel sometimes becomes a framing and drainage question before it becomes a tile question. We check floor structure and any moisture intrusion from hillside runoff before we commit to a layout.
Calabasas is in a Very High Fire Hazard Severity Zone, and post-Woolsey Fire rebuild standards apply to canyon homes. That mostly affects roofing and exterior work, but it also means we’re careful about venting, ignition-resistant details near the building envelope, and anything that touches the WUI code. Native coast live oaks are protected under the city’s oak-tree ordinances, so site work near a protected tree can trigger arborist review and setbacks – we account for that when a remodel touches exterior walls or adds a window. Permits run through the City of Calabasas, and inspection timelines for hillside projects can stretch. We pull the permits and pass the inspections; you don’t chase paperwork. Covering Calabasas means knowing the difference between a flat lot off Mulholland and a canyon property still stabilizing after a burn scar winter.
Serving Calabasas, CA – Our Local Coverage Area
We serve Calabasas and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Full Bathroom Remodeling in Calabasas
A full bathroom remodel in Calabasas typically takes 3 to 5 weeks of working time, plus permit review before demo begins. Hillside properties can add a week for inspection scheduling. Call (888) 427-1733 for a timeline specific to your home.
Yes, if you’re moving plumbing, electrical or walls, you need a permit from the City of Calabasas. A cosmetic refresh with no rough-in changes may not require one. We tell you up front which side of that line your project sits on, and we pull the permits.
Yes, and staying put keeps you closer to the $9,000 low end of the range. Keeping the toilet, sink and shower in their existing locations avoids slab or framing work. Changing the layout is where costs climb, so we price both versions if you’re undecided.
Full Bathroom Remodeling in Calabasas runs $9,000 – $28,000 depending on size, layout changes and material grade. Call (888) 427-1733 for an exact quote – estimates are free and itemized.
Every project is backed by our 730-Day Done Right Promise, one of the longest workmanship guarantees in residential construction. If something isn’t right, we come back and fix it. No fine print, no argument.
Get a Free Estimate on Full Bathroom Remodeling in Calabasas
Call (888) 427-1733 and a live person answers, day or night. We’ll schedule a free on-site estimate, measure the room, walk the plumbing and framing, and send you an itemized written quote so you know exactly what the number covers. Projects over $10,000 qualify for $1,000 off, and 0% financing for 18 months is available. Our technicians have up to 12 years of experience. Estimates are free, and there’s no obligation.