Walk-In Showers & Shower Remodeling in Santa Monica: What It Costs and How Long It Takes
Walk-In Showers & Shower Remodeling in Santa Monica runs $9,000 to $28,000, with most of our curbless doorless projects landing in the $14,000 to $20,000 range. A straightforward shower replacement finishes in 3 to 5 working days. A full tile-out with a curbless pan, relocated drain, and frameless glass takes 2 to 3 weeks because of the waterproofing cure time. Call (888) 427-1733 for a free on-site estimate and we’ll walk your alcove before quoting a number.
How the job actually runs, start to first shower
We don’t hand you a shopping list and disappear. Here’s the real sequence, day by day, so you know what to expect and what we need you to decide and when.
Day 1 – demo and rough-in. We pull the old tile, pan, and valve out, then open the wall to the studs. You’ve already picked your valve trim by now, so we set the rough-in plumbing and inspect the subfloor. If the old pan was leaking (common in 90404 bungalows), you’ll see the rot before we do.
Day 2 – framing and rough inspection. We correct out-of-square framing, block out for grab bars if you want them, and stage the drain. If the job pulls a permit (see below), the city inspects the rough plumbing and framing here. That inspection timing is the single biggest variable in your schedule.
Day 3 – waterproofing. We install a bonded membrane or a liquid-applied system over cement backer board, then flood-test or moisture-test before any tile goes up. This is the step nobody wants to rush and the one that determines whether the shower fails in 4 years or 20.
Days 4 to 12 – tile and finish. Wall tile, shower pan tile, grout, and cure. You’ve locked your tile selection and layout by now. We set fixtures after the membrane passes.
Days 13 to 15 – glass and final. Frameless glass gets templated after tile is set (never before), so expect a 5 to 10 day lead on custom glass fabrication. We install hardware, seal, and walk the job with you.
The homeowner decision points land at three moments: tile and valve selection before demo, drain linear vs. center before rough-in, and glass template after tile. Missing any one of those stalls the job.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll choose between
You’ll make about six real decisions. Each one has a trade-off, and there’s no universally right answer.
- Shower pan: curbless vs. low-curb. Curbless gives you the clean look and true accessibility, but it requires recessing the subfloor or building up a sloped pan, which adds $1,800 to $3,500 in labor and floor work. Low-curb is cheaper and works fine in most alcoves.
- Waterproofing: bonded membrane vs. liquid-applied. A sheet membrane is the industry’s most proven system and pretty forgiving on uneven studs. Liquid systems are cheaper on labor but demand a strict cure window. We install both.
- Tile: porcelain vs. natural stone. Porcelain at $6 to $18/square foot holds up to Santa Monica’s hard water better and never needs resealing. Marble and travertine at $15 to $40 run gorgeous but absorb mineral stains near the coast and require yearly sealing.
- Glass: frameless vs. semi-frameless. Frameless runs $1,200 to $3,400 for a custom panel and looks like the design showroom. Semi-frameless costs less but the metal track collects hard-water scale.
- Drain: center vs. linear. A linear drain costs $400 to $900 more but lets you use a single large-format tile on the floor with no cut pieces around a center drain.
- Fixtures: thermostatic vs. pressure-balance valve. Thermostatic valves ($300 to $800 more) hold exact temperature and suit households with kids or older adults. Pressure-balance is standard and does the job.
What Walk-In Showers & Shower Remodeling costs in Santa Monica, CA
Our Santa Monica Cost for Walk-In Showers & Shower Remodeling runs $9,000 to $28,000. Here’s the honest line-item breakdown.
| Scope | Typical range |
|---|---|
| Shower Replacement (like-for-like) | $3,000 – $8,500 |
| Walk-In Shower Installation (standard alcove) | $4,500 – $12,000 |
| Tub-to-Shower Conversion | $3,500 – $10,000 |
| Full Walk-In Showers & Shower Remodeling (curbless, tile, frameless glass) | $9,000 – $28,000 |
What pushes a job to the high end: relocating the drain or supply lines (adds $1,500 to $4,000), a curbless pan that needs subfloor work ($1,800 to $3,500), custom frameless glass with a return panel ($1,800 to $3,400), and full-floor tile extending into the bathroom. What keeps you at the low end: keeping the drain where it is, ceramic instead of stone, and a standard 60-inch alcove.
What’s included in our written estimate: tile and setting materials, waterproofing system, valve, trim, drain, labor, permit if required, and glass. What’s typically not: structural repair behind the wall if rot is found mid-demo, and design fees. We itemize both so the number you see is the number you pay – upfront pricing, no surprises.
See the difference
Before
After
Before
After
Before
AfterWhat Santa Monica homes specifically do to this job
Santa Monica’s housing stock shapes this work in ways inland contractors don’t anticipate. South of Wilshire in Ocean Park and the 90404 bungalows, we regularly find 1920s and ’30s homes where the shower was added over a porch or in a converted bath, and the subfloor under the pan was never properly rated for wet use. That means demo reveals rot, and a $12,000 shower can push toward $18,000 once framing gets replaced. The 90402 flats north of Montana often have 1980s remodels with the old lead-pan showers that need full re-waterproofing. And the coastal marine layer and salt air off the bay pit chrome and brass fittings faster than inland; we spec 316-grade stainless and PVD finishes on those jobs.
Two permit realities: interior shower work generally stays a bathroom-remodel permit, but anything in the coastal overlay near the beach can pull a Coastal Commission review on top of the city permit, and Santa Monica’s plan-check is known for moving slowly. We pull the permits and pass the inspections. If you’re reworking the wider space at the same time, this is part of a full Bathroom Remodeling in Santa Monica, and we scope both together from one set of drawings. Homeowners often pair this with Roof Replacement & Installation in Santa Monica while we’re already on the permit, especially in Ocean Park where the June Gloom cycle punishes older vent flashing. We also handle Bathroom Remodeling and Metal Roofing in Santa Monica across our Santa Monica service area.
Serving Santa Monica, CA – Our Local Coverage Area
We serve Santa Monica and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Walk-In Showers & Shower Remodeling in Santa Monica
A standard shower replacement takes 3 to 5 working days. A full curbless tile-out with frameless glass takes 2 to 3 weeks, because tile cure and glass fabrication add real calendar time. Plan for the permit inspection to add 3 to 10 days in Santa Monica’s plan-check queue. Call (888) 427-1733 for a schedule tied to your specific job.
Yes, most walk-in shower and shower remodeling work requires a bathroom permit in Santa Monica, especially anything that touches the drain, supply lines, or waterproofing over structural changes. We pull the permit and pass the inspection. Anything in the coastal overlay near the beach may also need Coastal Commission review. Call (888) 427-1733 to walk through the permit scope for your address.
Yes, and that’s how most of our Santa Monica clients stay under budget. Keeping the existing drain and supply lines in place saves $1,500 to $4,000 and often skips the plumbing inspection. We can replace the pan, waterproof, tile, and glass in the same alcove. Call (888) 427-1733 and we’ll tell you whether your layout can stay put.
It runs $9,000 to $28,000 for a full curbless tile and frameless glass remodel, with most jobs landing between $14,000 and $20,000. Smaller shower replacements start at $3,000 to $8,500. The big swings come from drain relocation, stone versus porcelain, and glass thickness. Call (888) 427-1733 for an exact quote – estimates are free.
Every Walk-In Showers & Shower Remodeling project we complete in Santa Monica is covered by our 730-Day Done Right Promise, one of the longest workmanship guarantees in residential construction. If anything fails in that window, we make it right. Call (888) 427-1733 and we’ll put the warranty in writing before the first tile goes up.
Ready to see your shower plan and price?
We’ll come to your Santa Monica home, measure the space, look at the subfloor and waterproofing reality, and hand you a written line-item estimate with a firm number – no surprises. Background-checked, uniformed technicians. Calls answered by a live person 24/7. Free design consult included. Call (888) 427-1733 to schedule your free estimate.
Written by the team at Groundwork Construction Co.